Saturday, 2 December 2017

3 weeks to go ...


... doors being hung, lots of painting and ramp/steps to main entrance ...
Door from main office into Waiting Area

Door and screen into Training Library and workspace

Counselling rooms first coat of paint ready for top coat next week.

Training Room plastered and nearly dry, ready for painting end of next week. Suspended ceiling installed.

Ramp and steps for main entrance progressing well now that site cabins have been moved.

Ramp and Steps from the front 

Wednesday, 15 November 2017

Site Visit

Some of the Network staff had a site visit and look around the latest progress on the building works earlier today.

In the corridor leading to the counselling rooms.

Taking a look into the new first floor counselling rooms.

The recently installed stairs with protection during the building works.

Thursday, 2 November 2017

Training Room kitchen area taking shape ...

Recess formed for kitchen area off Training Room. Electrics started. Don't worry the wall won't be yellow!

Windows installed and first coat of render ...

New partition for Counselling Office

New window for main office and reception.

First coat of render and windows installed in new build.

Stairs that go up and down ...

Stairs installed and ground floor underfloor heating and screed completed.


Temporary handrail, first floor underfloor heating pipework installed and floorboards started.

Monday, 16 October 2017

Site Visit ...

Anne and Louise enjoying a site visit to see progress. All still on programme

Thursday, 5 October 2017

The new build is now 3 days ahead ...

Roof trusses delivered 3 days early and some already installed but you cannot see them. The ones you can see are stored waiting to be installed.


Asbestos removed from the first floor and ready for Bristol Together ..

For those of you who are interested this is the underside of the first floor flat ceiling/roof but with the asbestos boards now safely removed. This was built in the late 1950's and is interesting as it is a construction method rarely seen here but often used in a similar form in Europe. 

Looking back into the old flat from the new opening into a large storage area above the old stage.

Inside the counselling corridor downstairs ....

Looking along corridor towards new Youth Counselling Room

Looking back down corridor towards the stairs and access

Monday, 25 September 2017

Up to first floor level ...

The walls for the new counselling rooms are now up to underside of the first floor.
Work is progressing well after a bit of a delay and the contractor is pretty much back on programme. The floor joists have been delivered to site and will be put up this week. The photo shows the walls on the new counselling rooms up to first floor level and a little beyond for the wall at the front.

3 weeks to go ...

... doors being hung, lots of painting and ramp/steps to main entrance ... Door from main office into Waiting Area Door and screen in...